Data as of 12/31/2019

Abbotts Creek Elementary (E-20)

Key Facts:

9900 Durant Road
Raleigh, NC 27614

Type: New School
Acreage: 12.50
New Sq. Ft. : 103,724
Plan: 2013
Budget: $21,336,178
Architect: Clark Nexsen
Contractor: Barnhill Contracting
 

Project Milestones:

Start Design: Apr. 20, 2013
Notice to Proceed: Jun. 18, 2014
Occupied: Aug., 2015


Project Summary:

New Clark Nexsen 3-story prototype elementary school , based on the Alston Ridge prototype, to be built on Durant Road in Raleigh.

Project Status:

This project is complete.

Schedule:



Budget

Item Original Budget Current Budget Committed Budget
Total $24,280,977 $21,336,178 $21,304,125
Design $977,454 $1,133,331 $1,133,331
Construction $17,693,748 $15,018,890 $15,018,890
Misc. Contracts $564,671 $879,557 $879,557
FF&E $2,895,368 $2,469,400 $2,469,400
Public Infrastructure $1,408,758 $1,835,000 $1,802,947
Municipal $0 $0 $0
Sub Total $23,539,999 $21,336,178 $21,304,125
Land $740,978 $0 $0