Data as of 7/31/2017

Buckhorn Creek Elementary (E-45)

Key Facts:

5651 Honeycutt Road
Holly Springs, NC 27540

Type: New School
Acreage: 22.00
New Sq. Ft. : 112,598
Plan: 2013
Budget: $35,917,640
Anticipated Occupancy: Aug, 2018
Architect: Moseley Architects
Contractor: Balfour Beatty
 

Project Milestones:

Start Design: Dec. 2, 2015
Notice to Proceed: May. 3, 2017


Project Summary:

This will be the third use of the Moseley Architects prototype - 780-student elementary school, with a core to support 900. It has three classroom wings that will be perpendicular to the main corridor. Two wings will be two-stories.

Project Status:

"Site: Storm Drain complete along the west side of the site. Strom Drain continues on the east side of site. Water Line is continuing on the west side of the site. Grading work on north side is progressing and nearing completion. Topsoil screening nearing completion

Schedule:



Budget

Item Original Budget Current Budget Committed Budget
Total $23,821,082 $35,917,640 $28,101,850
Design $1,014,638 $1,194,800 $1,070,520
Construction $17,763,618 $26,123,216 $26,121,610
Misc. Contracts $586,299 $1,116,957 $498,049
FF&E $3,005,514 $2,781,068 $0
Public Infrastructure $1,451,013 $4,701,599 $411,671
Municipal $0 $0 $0
Sub Total $23,821,082 $35,917,640 $28,101,850
Land $0 $0 $0