Data as of 04/30/2018

Buckhorn Creek Elementary (E-45)

Key Facts:

5651 Honeycutt Road
Holly Springs, NC 27540

Type: New School
Acreage: 22.00
New Sq. Ft. : 112,598
Plan: 2013
Budget: $35,917,640
Anticipated Occupancy: Aug, 2018
Architect: Moseley Architects
Contractor: Balfour Beatty
 

Project Milestones:

Start Design: Dec. 2, 2015
Notice to Proceed: May. 3, 2017


Project Summary:

This will be the third use of the Moseley Architects prototype - 780-student elementary school, with a core to support 900. It has three classroom wings that will be perpendicular to the main corridor. Two wings will be two-stories.

Project Status:

Started tree planting onsite. Pipe and duct insulation in progress in area B. The kitchen hood and cooler / freezer installation has been scheduled. Field measuring for casework is completed. The classroom ceiling grid & light installation has been completed in Area C. Above Ceiling Inspection preparation in progress. Drywall completion 80% on 2nd floor in Area D. Window installation is complete. Overhead rough in is ongoing. Wall raming is in progress on level two of Area E. Exterior brick veneer has been completed and the window installation is ongoing. Overhead Rough in is in progress on the first floor based on the easement update we received this week the permanent power will not be completed until late April 2018. This has pushed the finishes of the building due to the power needs for the Air handlers. The team is currently exploring options to mitigate this impact.

Schedule:



Budget

Item Original Budget Current Budget Committed Budget
Total $23,821,082 $35,917,640 $32,726,671
Design $1,014,638 $1,194,800 $1,086,120
Construction $17,763,618 $26,123,216 $26,121,610
Misc. Contracts $586,299 $1,122,198 $549,403
FF&E $3,005,514 $2,775,827 $1,406,710
Public Infrastructure $1,451,013 $4,701,599 $3,562,828
Municipal $0 $0 $0
Sub Total $23,821,082 $35,917,640 $32,726,671
Land $0 $0 $0