Data as of 5/31/2017

Buckhorn Creek Elementary (E-45)

Key Facts:

5651 Honeycutt Road
Holly Springs, NC 27540

Type: New School
Acreage: 22.00
New Sq. Ft. : 112,598
Plan: 2013
Budget: $35,917,641
Anticipated Occupancy: Aug, 2018
Architect: Moseley Architects
Contractor: Balfour Beatty
 

Project Milestones:

Start Design: Dec. 2, 2015
Notice to Proceed: May. 3, 2017


Project Summary:

This will be the third use of the Moseley Architects prototype - 780-student elementary school, with a core to support 900. It has three classroom wings that will be perpendicular to the main corridor. Two wings will be two-stories.

Project Status:

CM has submitted GMP 2 for the building for WCPSS BOE on May 2nd, 2017.  Remaining bid packages for site and off-site GMP 3 will bid May 2nd for BOE approval on May 16th, 2017.

Schedule:



Budget

Item Original Budget Current Budget Committed Budget
Total $23,821,082 $35,917,641 $27,998,551
Design $1,014,638 $1,194,800 $1,070,520
Construction $17,763,618 $26,123,217 $26,121,611
Misc. Contracts $586,299 $1,116,957 $496,249
FF&E $3,005,514 $2,781,068 $0
Public Infrastructure $1,451,013 $4,701,599 $310,171
Municipal $0 $0 $0
Sub Total $23,821,082 $35,917,641 $27,998,551
Land $0 $0 $0