Data as of 12/31/2017

Buckhorn Creek Elementary (E-45)

Key Facts:

5651 Honeycutt Road
Holly Springs, NC 27540

Type: New School
Acreage: 22.00
New Sq. Ft. : 112,598
Plan: 2013
Budget: $35,917,640
Anticipated Occupancy: Aug, 2018
Architect: Moseley Architects
Contractor: Balfour Beatty
 

Project Milestones:

Start Design: Dec. 2, 2015
Notice to Proceed: May. 3, 2017


Project Summary:

This will be the third use of the Moseley Architects prototype - 780-student elementary school, with a core to support 900. It has three classroom wings that will be perpendicular to the main corridor. Two wings will be two-stories.

Project Status:

Area A - Drywall hanging is complete, Windows are complete, and Brick cleaning is complete. Drywall finishes in nearing complete and Ceiling Grid to start 1/15. Area B - Pipe and duct insulation in progress, Windows are complete, Sprinkler rough in is in progress. Brick cleaning is complete, and Misc. steel supports are in progress. Area C - Drywall hanging is complete, Windows are nearing completion. Pipe and Duct insulation are in progress. Area D - Overhead trade rough is continuing on the first floor, Framing is complete on the first floor and in progress on the second. Brick is in progress, Lightweight roof concrete is complete, and Roof Membrane in progress. Area E - Roof Deck in progress, Slab on deck pour is complete and Exterior metal stud framing in progress.

Schedule:



Budget

Item Original Budget Current Budget Committed Budget
Total $23,821,082 $35,917,640 $28,205,069
Design $1,014,638 $1,194,800 $1,086,120
Construction $17,763,618 $26,123,216 $26,121,610
Misc. Contracts $586,299 $1,124,957 $500,238
FF&E $3,005,514 $2,773,068 $0
Public Infrastructure $1,451,013 $4,701,599 $497,101
Municipal $0 $0 $0
Sub Total $23,821,082 $35,917,640 $28,205,069
Land $0 $0 $0