Data as of 08/31/2019

Bryan Road Elementary (E-31)

Key Facts:

8317 Bryan Road
Garner, NC 27529

Type: New School
Acreage: 45.87
New Sq. Ft. : 109,432
Plan: 2013
Budget: $29,095,145
Architect: Clark Nexsen
Contractor: New Atlantic
 

Project Milestones:

Start Design: Dec. 18, 2014
Notice to Proceed: Feb. 3, 2016


Project Summary:

New 52-classroom school on Bryan Road in Garner. Version of this prototype previously built at Abbotts Creek Elementary. This campus will be used as swing space for the students and staff of Vandora Springs Elementary, beginning Spring Break, 2017. It will open for its new population in Fall, 2018.

Project Status:

Project completed.

Schedule:



Budget

Item Original Budget Current Budget Committed Budget
Total $24,594,308 $29,095,145 $27,458,511
Design $1,589,353 $1,549,959 $1,540,389
Construction $17,912,384 $19,303,933 $19,196,309
Misc. Contracts $636,044 $577,974 $567,599
FF&E $3,005,514 $3,006,614 $2,151,827
Public Infrastructure $1,451,013 $4,475,000 $3,820,722
Municipal $0 $181,664 $181,664
Sub Total $24,594,308 $29,095,145 $27,458,511
Land $0 $0 $0